Precast façades, four levels at a time

How the Aster Court envelope goes up in the gaps between tower-crane lifts.

Written by

Karim Haddad

At Aster Court the concrete frame and the façade share one tower crane. Getting both up on time is a question of choreography.

The sequence

A floor is poured every nine days. For the three days after a pour the crane is free, and that is when the façade gang takes over, lifting the deep balcony panels into place four levels below the wet deck.

Fixing and sealing

Each panel hangs on two cast-in brackets and is restrained at the bottom. Joints are sealed from mast climbers, which follow the panels up the building.

Weather

Panels cannot be lifted in winds above thirty-eight kilometres an hour. We keep a five-day float in the programme for it and have used three so far.

Progress

Block A is complete. Block B is at level nine and on programme.

Keep reading

More from the journal.

The three most recent pieces, newest first.

The three most recent pieces, newest first.

Start a project

Have a site, a sketch or just a question?

Or call 0161 496 0127

Start a project

Have a site, a sketch or just a question?

Or call 0161 496 0127

Massif

Design and build contractor for homes, workplaces and public buildings across the North of England.

Massif

© 2026 Massif Construction Ltd. Registered in England, no. 04417328.

© 2026 Massif Construction Ltd. Registered in England, no. 04417328.

Massif, a Framer template by Ajoy

Massif, a Framer template by Ajoy

Create a free website with Framer, the website builder loved by startups, designers and agencies.