At Aster Court the concrete frame and the façade share one tower crane. Getting both up on time is a question of choreography.
The sequence
A floor is poured every nine days. For the three days after a pour the crane is free, and that is when the façade gang takes over, lifting the deep balcony panels into place four levels below the wet deck.
Fixing and sealing
Each panel hangs on two cast-in brackets and is restrained at the bottom. Joints are sealed from mast climbers, which follow the panels up the building.
Weather
Panels cannot be lifted in winds above thirty-eight kilometres an hour. We keep a five-day float in the programme for it and have used three so far.
Progress
Block A is complete. Block B is at level nine and on programme.