For fourteen months our site at Fenwick Primary shared a fence with a playground. This is what that meant day to day.
The rules we agreed
No deliveries between 8.15 and 9.15 or between 2.45 and 3.45. No crane lifts at break or lunch. Every operative checked and badged, and a single gate with a full-time marshal.
What we moved to the holidays
The timber frame arrived as flat panels and went up in eleven days over Easter. Demolition of the old boiler house waited for the summer. Anything that shook the ground was planned around the exam weeks.
The part nobody planned
The children were fascinated. Our site manager ended up giving an assembly every half term, and a Year 4 class named the excavator.
What we would do again
All of it. The programme was two weeks longer than a clear site would have allowed, and not one school day was lost.