Marsh Lane Depot
A steel portal-frame distribution depot with a solar roof and forty dock doors, on reclaimed dock land.
On site now
Client
Nordvest Logistics
Sector
Industrial
Location
Hull
Size
11,400 m²
Contract value
£9.7m
On site for
50 weeks
On site this week
Steel frame, bays 3 to 6
Programme
Programme
The brief
Nordvest needed 11,400 square metres of cross-dock warehouse within reach of the port, ready for the 2027 peak season.
How we are building it
The ground is made-up dock land, so the slab sits on 380 driven piles. A buried dock wall turned up during piling. We redesigned the pile layout around it within a week and held the programme.
Steel erection is working from the east gable. Bays one and two are clad, and bays three to six are going up now.
What comes next
The roof and its solar array follow the steel, with the dock levellers and yard to finish. Handover is programmed for June 2027.
They found the old dock wall in week two and had a redesign priced by week three. No drama.
Ingrid Solberg, Nordvest Logistics