Hover for the drawing

All projects

Holloway Terrace

Eighteen three-bedroom townhouses on a former bus depot, sold off plan and lived in within a week of the last coat of paint.

Client

Brightwater Homes

Sector

Residential

Location

York

Size

18 townhouses

Contract value

£5.9m

On site for

52 weeks

Programme

How the build was sequenced, trade by trade

Week 0Week 13Week 26Week 39Week 52
Groundworks
Frame
Envelope
Mechanical and electrical
Fit-out
Externals and handover
Complete Under way To comeHanded over · 52 weeks

The brief

Brightwater bought a contaminated depot site with planning for eighteen houses. They needed the ground cleaned, the houses built, and keys in buyers’ hands inside a year.

How we built it

We removed the old fuel tanks and capped the ground in the first six weeks, then ran three gangs of bricklayers in sequence so that each terrace was a fortnight behind the last.

Kitchens and bathrooms were fitted by our own joiners rather than a supply-and-fit firm, which is why the snag lists stayed short.

The result

All eighteen homes were completed in fifty-two weeks. The last buyer moved in six days after practical completion.

Every house was handed over with fewer than five snags. Our customer care team had almost nothing to do.

Laura Finch, Brightwater Homes

Next project

Mill Lane Extension

Start a project

Have a site, a sketch or just a question?

Or call 0161 496 0127

Start a project

Have a site, a sketch or just a question?

Or call 0161 496 0127

Massif

Design and build contractor for homes, workplaces and public buildings across the North of England.

Massif

© 2026 Massif Construction Ltd. Registered in England, no. 04417328.

© 2026 Massif Construction Ltd. Registered in England, no. 04417328.

Massif, a Framer template by Ajoy

Massif, a Framer template by Ajoy

Create a free website with Framer, the website builder loved by startups, designers and agencies.